Venture Global Begins Plaquemines LNG Phase 1 Commercial Operations, Shell Lifts First Long-Term Cargo

Venture Global declared commercial operations for Phase 1 of Plaquemines LNG on October 31, moving the Louisiana project from commissioning into long-term contracted service; Shell lifted the first post-COD cargo.

Published by Allstream Insiders

Allstream Insiders Summary

Venture Global commenced commercial operations of Phase 1 of its Plaquemines LNG export project in Plaquemines Parish, Louisiana, on October 31, 2026. According to the company’s November 1 announcement, the milestone enables sales to Phase 1’s long-term customers and was reached just over 53 months after the Phase 1 final investment decision.

The first cargo after the commercial-operations date departed October 31 and was lifted by Shell. The declaration is distinct from the plant’s earlier commissioning production and cargoes: it marks the transition of Phase 1 into its long-term sales and purchase agreement, or SPA, period.

The announcement does not declare commercial operations for Plaquemines Phase 2, announce a new final investment decision, or identify new engineering, construction, equipment or service awards. Venture Global had previously targeted Phase 2 commercial operations for mid-2027; that remains a company target, not a completed milestone.

Plaquemines Phase 1 commercial operations at a glance

Item Company-reported detail
Facility Plaquemines LNG, Venture Global’s second LNG export project
Location Plaquemines Parish, Louisiana, approximately 20 miles south of New Orleans
Phase 1 commercial-operations date October 31, 2026
Time from Phase 1 FID to COD Just over 53 months
First post-COD long-term cargo Lifted by Shell
Entire Plaquemines facility Venture Global describes the completed facility as expected to have export capacity of more than 28 million tonnes per annum, with potential for expansion
Phase 2 status Not included in the October 31 commercial-operations declaration; previously targeted for mid-2027 COD

What changed with the commercial-operations declaration?

Commercial operations is a contractual and operational milestone, not merely a first-production or commissioning event. Plaquemines began producing LNG and exporting commissioning cargoes before the October 31 declaration. With Phase 1 now at COD, Venture Global said it has begun selling LNG to the phase’s long-term customers under the applicable SPAs.

That distinction matters because a facility can produce LNG during commissioning while systems, performance testing and other work continue. The October declaration establishes that Phase 1 has reached the company’s stated commercial milestone for its long-term contracted service.

Shell’s first post-COD lift confirms the start of that next operating period. The announcement does not disclose the cargo volume, destination, SPA pricing, the full Phase 1 customer schedule or the allocation of future cargoes among long-term buyers.

What is included in Plaquemines LNG?

The broader Plaquemines development is a large-scale Louisiana liquefaction and export facility on the Mississippi River. Venture Global describes the approximately 630-acre site as having deep-water access and potential export capacity of more than 28 million tonnes per annum once the overall facility is complete. Its facility description identifies liquefaction trains, LNG storage, marine-loading berths, inside-the-fence power generation, gas pretreatment and Gator Express pipeline connections.

Those broader facility details provide context for the October 31 Phase 1 milestone. They should not be read as new work awards or as confirmation that all remaining construction, commissioning, expansion or permitting activity is complete.

What remains separate from the Phase 1 milestone?

Plaquemines Phase 2 remains a separate commercial-operations milestone. In its second-quarter 2026 results, Venture Global said it was targeting Phase 2 COD in mid-2027. That timing is forward-looking and could be affected by construction, commissioning, performance testing, approvals and other execution factors.

Venture Global also has a separate Plaquemines Expansion proposal in the FERC review process. The Phase 1 COD announcement does not approve that expansion, establish an expansion FID, authorize construction or announce associated supplier awards.

Allstream perspective: The milestone shifts attention from construction to reliable operations

Allstream perspective: For the completed Phase 1 scope, the commercial-operations declaration changes the primary market focus from project delivery to safe, reliable, long-term operation. The ongoing requirements of an LNG export plant can involve operations and maintenance services; rotating-equipment and power-island support; controls and instrumentation; inspection and integrity programs; marine and terminal services; pipeline transportation; storage and loading systems; and turnaround planning.

Those categories describe the types of work an operating LNG facility may require; they are not new procurement announcements or contractor awards from Venture Global. Near-term commercial visibility for the remaining Plaquemines scope will depend on Phase 2 COD progress, operational updates, maintenance strategies, any newly announced contracts and the outcome of separate expansion permitting and financing decisions.