ExxonMobil says production has started at Uaru, its fifth offshore Stabroek Block development, while the Errea Wittu FPSO is expected to reach 250,000 barrels per day of initial capacity in the first quarter of 2027.
Published by Allstream Insiders
Allstream Insiders Summary
ExxonMobil has started production at Uaru, the fifth development in Guyana’s offshore Stabroek Block. According to ExxonMobil’s November 15 announcement, the startup of the Errea Wittu floating production, storage and offloading vessel, or FPSO, raises Guyana’s installed offshore production capacity to 1.1 million barrels per day.
Installed capacity is not the same as current daily production. ExxonMobil said Errea Wittu is expected to achieve its 250,000-barrel-per-day initial production capacity in the first quarter of 2027. The company did not provide a current Uaru production rate, a ramp-up schedule beyond that expectation, or a new contractor or equipment award in the announcement.
Errea Wittu is the fifth FPSO operating for the Stabroek Block, joining Destiny, Unity, Prosperity and ONE GUYANA. ExxonMobil Guyana operates the block with a 45% interest; Hess Guyana Exploration holds 30%, and CNOOC Petroleum Guyana holds 25%.
Uaru and Errea Wittu at a glance
| Item | Company-reported detail |
|---|---|
| Development | Uaru, ExxonMobil’s fifth development in the offshore Stabroek Block |
| Production status | Production startup announced November 15, 2026 |
| FPSO | Errea Wittu |
| Expected initial production capacity | 250,000 barrels per day, expected in the first quarter of 2027 |
| FPSO storage capacity | 2 million barrels |
| Guyana installed production capacity after startup | 1.1 million barrels per day |
| Stabroek Block interests | ExxonMobil Guyana 45%; Hess Guyana Exploration 30%; CNOOC Petroleum Guyana 25% |
What the Uaru startup establishes—and what it does not
The announcement establishes that Uaru has entered production. It also identifies Errea Wittu as an operating FPSO and says the vessel increases the country’s installed capacity to 1.1 million barrels per day.
However, the release does not say that Uaru is already producing 250,000 barrels per day. That figure is the FPSO’s expected initial production capacity, with ExxonMobil projecting achievement in the first quarter of 2027. Actual production during a startup and ramp-up period can differ from installed capacity because of commissioning, well performance, operating conditions and other project variables.
The announcement also does not provide Uaru’s capital cost, the number of wells, subsea scope, current production volume, export-lifting schedule, or newly awarded engineering, construction or supply packages. Those items should not be inferred from the startup announcement alone.
Fifth FPSO expands the operating base offshore Guyana
Errea Wittu joins the Destiny, Unity, Prosperity and ONE GUYANA FPSOs in the Stabroek Block. ExxonMobil said the vessel’s name means “abundance” in the Warrau language and that it has storage capacity of two million barrels.
The step from four to five producing developments is significant operationally: it adds another offshore production and storage asset to the Guyana operating base. Still, the reported 1.1 million barrels per day is an installed-capacity measure. It should not be presented as a reported national production rate for a particular day or month.
Longtail is a separate, later development
ExxonMobil also said it recently made a final investment decision on Longtail, the eighth planned Stabroek Block development. Longtail is separate from Uaru: Uaru is now in the production-startup stage, while Longtail remains a future development.
In its Longtail announcement, ExxonMobil said the project had received the required government and regulatory approvals, is expected to start up in 2030, and carries planned investment of about $12.5 billion. The company said Longtail is expected to use an FPSO designed to process 1.2 billion standard cubic feet per day of gas and produce up to 250,000 barrels per day of condensate, with approximately 45 subsea production and injection wells.
Those Longtail details should not be applied to Uaru. They describe a different project and remain subject to ExxonMobil’s stated forward-looking risks and execution conditions.
Local supply-chain context
ExxonMobil said that, since 2015, its Stabroek Block co-venturers have spent more than $3.9 billion with Guyanese vendors. The company also said Errea Wittu marks MODEC’s entry into the Guyana market.
These statements provide context on the existing local and international supply base supporting Stabroek operations. They do not announce a new Uaru contract, identify the value of a MODEC contract, or establish new procurement opportunities.
Allstream perspective: operating activity rises while the next project pipeline advances
Allstream perspective: Uaru’s production startup moves the fifth Stabroek development from construction and commissioning into operations. That transition can support continuing demand for offshore operations and maintenance, marine and aviation logistics, inspection, integrity management, subsea support, rotating-equipment service, instrumentation, controls, electrical systems and safety-related services. The announcement does not identify a newly awarded scope in any of those categories.
Separately, the sanctioned Longtail project illustrates the longer-term development pipeline. If its disclosed plan proceeds, project execution could involve engineering and design; FPSO and topsides fabrication; subsea trees, manifolds, umbilicals, flowlines and risers; wells and completion services; mooring systems; power generation and electrical equipment; compression and process equipment; marine logistics; and installation and commissioning services. ExxonMobil has not used the Uaru startup announcement to award or identify suppliers for those potential scopes.
For the industrial market, the next decision-useful updates will be Uaru’s reported ramp-up progress, operating milestones across the existing FPSO fleet, and project-specific Longtail contracting, fabrication, drilling, subsea and installation disclosures. Until then, the Uaru release is best read as a confirmed production startup and installed-capacity milestone—not as evidence of new construction awards.